Building the Extension: Week 12

The windows go in, and plastering starts.

27 September: Windows installed.

Windows! Porch frame installed.
Rear window Front and side windows
Front window Rear window.

28 September: Plasterboarding.

Boarding walls and ceiling Back room

29 September: Plastering begins.

Render completed around windows Plastering begins in hall
A beautifully shaped ceiling in the back room Ben's room's ceiling is started.
Atrium started Shower room ceiling completed

30 September: Plastering continues.

Crumbling old plaster removed from hall Shower tray installed
Ben's room Back room

1st October: Plastering continues.

Garage ceiling boarded Utility room ceiling boarded
Skimming complete in back room... and in Ben's room

2st October: Side wall painted

Side wall painted